Target Date |
|
Task to be Completed |
|
|
2005 |
Date Completed |
|
|
|
15 June |
In Progress |
Definitions and limitations: Agreed on
nomenclature, limits of the study, dates for the route that best represents
the trail as it existed in Arkansas during the period being examined |
9 |
| 30 August |
In Progress |
Identified extant portion and probability of
route where evidence exists for non-extant route(s) |
1 |
| 30 November |
In Progress |
Located and identified existing markers,
memorials, cemeteries and other landmarks for inclusion in mapping and
documentation |
1 |
| 31 December |
In Progress |
Made physical on-site observation of the agreed
on route in its entirety; documented with GPS and UTM coordinates; made
observations and recommendations for review |
7 |
|
2006 |
|
|
|
| 31 January |
In Progress |
Completed general survey of known archeological
sites; communicated with and collaborated with AAS for inclusion of
"chapter" on prehistoric trail use but also Native American resettlement in
the region |
5 |
| 28 February |
In Progress |
Completed mapping and location tasks; completed
working map |
7 |
| |
|
|
|
| 6-7 March |
|
First Project Review and Planning |
3 |
| |
|
|
|
| 15 March |
|
Agreed on outline for Published Document |
7 |
| 1 Apr |
|
Communicated with AHPP for National Historic
Trail review and status |
4 |
| 30 May |
|
Reviewed collected documentation to date and
made preliminary writing assignments |
4 |
| 1 August |
|
Presented writing samples of worked completed to
date |
4 |
| 1 September |
|
Began publisher communication |
3 |
| 1 October |
|
Solicited readers for peer review |
5 |
|
2007 |
|
|
|
| 8,9 January |
|
Second Project Review and Planning |
4 |
| |
|
|
|
| 30 January |
|
Received and reviewed first draft portions for
team reading, recommendations and review |
9 |
| 1 April |
|
Secured necessary permissions for copyright
purposes for publication |
5 |
| 30 April |
|
Communicated with local historic organizations
about information and/or presentations |
7 |
| 30 April |
|
Received document portions for final review and
corrections |
4 |
| 20 May |
|
Completed document draft |
4 |
| 1 June |
|
Submit draft to Readers |
5 |
| 31 October |
|
Received peer reviews, made correction and made
final group review |
5 |
| |
|
Notified and queried agencies for route status
review |
4 |
| 31 October |
|
Document submitted to publisher |
4 |
| |
|
|
|
| 8 October |
|
Third Project Review and Planning |
7 |
|
2007-2008 |
|
|
|
| TBA |
|
Agreed on standard wayside markers and signs and
route markers |
7 |
| TBA |
|
Solicited and made presentations to local and
regional historical groups |
7 |
| TBA |
|
Solicited AHPP participation in brochure for
route/tourism |
4 |
| 1 June |
|
Prepared and distributed limited public releases
for 2009 |
4 |
| TBA |
|
Solicited and collaborated with local
historical societies to secure and place markers |
9 |
| 8 October |
|
Published document release date |
|
| |
|
|
|
| 12, 13 November |
|
Fourth Project Review and Panning |
9 |
|
2009 |
|
|
|
| January |
|
Route designations in place, markers in place,
brochures completed and distributed, informational web site completed. |
|
| |
|
|
|